Conversion of a multi-storey shopping center in Gevelsberg
As part of the conversion of a multi-storey shopping center in Gevelsberg, Knepper is carrying out, among other things, the gutting and partial demolition of the sales floors.
Work carried out
- Complete gutting of the sales floors
- Dismantling of all floor coverings and superstructures
- Demolition of load-bearing and non-load-bearing masonry
- Installation of temporary steel bracing structures
- Mechanical partial demolition of the building complex over several floors
Machines in use
- Longfront demolition excavator > 28 m
- Tracked excavators up to 30 tons with OilQuick attachments
- Compact equipment up to 8 tons with OilQuick attachments
- Various small equipment
- Lifting platforms up to 15 m working height