Demolition of burnt-down factory building in Iserlohn

Knepper opted for a comprehensive, sustainable solution for site restoration when dismantling the burnt-down WEKA factory buildings in Iserlohn.

Work carried out

  • Clearing the site of the debris / waste piles remaining after the fire in 2009 (PFC-contaminated from extinguishing water impact)
  • Dismantling of the remaining building and plant components
  • Dismantling of the area sealed with steel plates
  • Creation of test excavations and subsequent restoration of the sealed surface by asphalting

To the service overview

Machines in use

  • Longfront demolition excavator > 20 m
  • Tracked excavators up to 40 tons with OilQuick attachments
  • Compact machines, small equipment and working platforms

Your contact person

SALES DEMOLITION AND DISMANTLING
Phone: +49 2941 2841-310
E-Mail: vertrieb@knepper-gruppe.de 