Lightening and dismantling of bridge superstructure

Together, we dismantled an old steel bridge under challenging conditions.

Work carried out

  • Dismantling and disposal of a steel bridge superstructure in 24-hour operation
  • Earthworks for 700 tons crawler crane
  • Partial demolition of abutment

To the service overview

Machines in use

  • Excavator 50 tons and 40 tons
  • Terex CC3800 crawler crane (provided by the client)
The project in detail

Together with our customer Heinrich Send, we dismantled an ageing steel bridge in 24-hour shift operation. The project presented us with a number of challenges due to the limited space and tight time frame.

But the plan worked: First, our earthworks team prepared an approximately 50-meter-long gravel bed as a storage area for the segments to be dismantled. Once we had removed the concrete roadway and sidewalks, the lightened structure could finally be pulled by a Terex CC3800 crawler crane from Franz Bracht. Our team then worked in 24-hour shifts to dismantle the superstructure segments, which weighed over 100 tons, and took over the partial dismantling of the abutments. We are delighted that our joint project with Heinrich Send worked so well and would like to thank them for their close cooperation!