Knepper developed a comprehensive dismantling concept for a shaft furnace system and a 60-meter-high industrial chimney and planned all measures.
Work carried out
- Dismantling of a 60 m high steel industrial chimney and blasting of a 30 m high, statically significantly impaired shaft furnace battery
- Complete conception of the measure and creation of a detailed dismantling concept
- Complete dismantling and disposal of the plant including asbestos removal in accordance with TRGS 519
Machines in use
- Tracked excavators up to 50 tons with OilQuick attachments
- Lifting platforms up to 42 m working height
- Own construction site logistics
- Mobile crushing and screening technology