The project required the use of specialized technology and thorough refurbishment measures to prepare parts of the structure for reuse.
Work carried out
- Crane-supported dismantling of a clinker bridge after fire damage and a cross bridge at a height of 40 m
- Cleaning of the steel structure with special H-suction cleaners in accordance with TRGS 519
- Construction was partly reused
Machines in use
- Asbestos removal technology
- Mobile cranes up to 300 tons
- Mobile working platform